<thead id="31jd1"></thead>
<cite id="31jd1"></cite><cite id="31jd1"></cite>
<menuitem id="31jd1"><i id="31jd1"></i></menuitem>
<cite id="31jd1"></cite>
<cite id="31jd1"><i id="31jd1"><span id="31jd1"></span></i></cite>
<listing id="31jd1"><i id="31jd1"></i></listing>
<cite id="31jd1"></cite>
<listing id="31jd1"></listing>
<var id="31jd1"><ruby id="31jd1"><address id="31jd1"></address></ruby></var>
<listing id="31jd1"><i id="31jd1"><video id="31jd1"></video></i></listing>
<thead id="31jd1"></thead><thead id="31jd1"><dl id="31jd1"><noframes id="31jd1">
<listing id="31jd1"></listing><thead id="31jd1"><del id="31jd1"><span id="31jd1"></span></del></thead>
<var id="31jd1"></var>
<progress id="31jd1"><del id="31jd1"></del></progress><listing id="31jd1"><ruby id="31jd1"><span id="31jd1"></span></ruby></listing><listing id="31jd1"></listing>
<listing id="31jd1"><ruby id="31jd1"><span id="31jd1"></span></ruby></listing>
<thead id="31jd1"><ruby id="31jd1"></ruby></thead><thead id="31jd1"></thead>

综合管理平台 | 企业邮箱 | 收藏本站 | 网站管理 | 会员中心

新闻动态
联系方式

电 话:0379—66994811
电子邮件:gcjsjt@lljl.com.cn

您现在的位置:首页新闻动态公司要闻图片新闻 > 洛阳石化炼油结构调整项目渣油加氢装置 干气脱硫塔吊装一次成功

洛阳石化炼油结构调整项目渣油加氢装置 干气脱硫塔吊装一次成功

作者:乔新奇日期:2019-06-27 09:18

2019年6月25日下午15时10分,洛阳石化炼油结构调整项目渣油加氢装置干气脱硫塔顺利起吊,通过各参建单位的紧密协作,下午16时两台干气脱硫塔全部吊装就位。

干气脱硫塔直径1米,高26.9米,采取130吨吊车主吊,50吨吊车遛尾的方式吊装,是渣油加氢装置第一个设备吊装作业。为确保设备吊装万无一失,安装监理工程师郭玄武一是在吊装前按设计文件仔细核对螺栓间距,并复核设备裙座上螺栓孔间距,确保设备与基础相匹配;二是在吊装期间不辞劳苦全程旁站,确保吊装安全,最终实现了设备的一次吊装就位。

渣油加氢装置作为炼油结构调整项目的第一个开工装置,各参建单位高度重视。在土建施工阶段,项目监理部全体人员加强过程控制,严格验收每个施工工序,克服了人员少、任务重的困难,通过一次次的纠偏改错,保证了土建施工质量,实现了本装置各单元土建交安一次完成。

此次渣油加氢装置干气脱硫塔的顺利吊装为后续安装施工打下了良好基础,我项目监理部将进一步加强现场质量和安全管控,以实际行动推动项目建设的有序进行。